Reference formulas and worked examples below keep their stated units. Monetary examples use USD; dimensional examples use US customary units unless labeled otherwise. Metric calculator inputs are converted to these reference units before calculation. Choosing another currency does not convert example amounts or exchange money.
How to use this concrete footing calculator
Select a geometry, enter dimensions and the number of matching elements, then add your material allowance. Dimensions are inputs to the estimate, not a structural recommendation.
How the calculation works
Strip volume = length × width × depth. Rectangular pad volume uses the same prism formula. Round volume = π × (diameter ÷ 2)² × depth. Convert dimensions into a consistent unit before multiplying.
Multiply by matching elements and then by (1 + allowance percentage ÷ 100). Divide cubic feet by 27 for cubic yards, or multiply by 0.028316846592 for cubic meters.
Whole bags = adjusted concrete volume ÷ the entered mixed bag yield, rounded up. Bag cost uses whole bags; bulk material cost uses required volume in the supplier’s selected pricing unit.
Worked example
One 40 ft strip, 16 in wide and 8 in deep, contains 35.5556 cu ft. With 10% extra, the order estimate is 39.1111 cu ft (1.4486 cu yd). At 0.6 cu ft yield, that is 66 whole bags. At $7 per bag, bagged material is $462.
Limits and assumptions
Geometric takeoff only. It does not select footing dimensions, load capacity, soil bearing, frost depth, reinforcement or compliance with building rules. Subtract overlapping volumes before entering repeated strip lengths. Material prices are examples; delivery minimums and site costs are not included.
Frequently asked questions
Can I calculate several matching pads or piers?
Yes. Enter their count. If sizes differ, calculate each group separately and combine unrounded volumes before ordering.
Does the tool choose a safe footing size?
No. Use dimensions from your project design. Soil, loads, frost and reinforcement are not modeled.
Why is bulk cost lower than a delivered quote?
It includes only the required volume times the entered unit price. Supplier minimums, delivery, pump charges, labor and taxes must be allowed for separately.
Can I use metric inputs?
Yes. Choose Metric in Currency & units. Dimensions, bag yield and displayed volumes convert; the supplier pricing unit stays explicitly selected.
References
QUIKRETE Concrete Mix #1101: manufacturer bag-yield specifications